Key performance indicators for 2019

Company KPI Execution

The performance of Rosseti Centre is estimated on the basis of key performance indicators, the structure and planned values of which are approved annually by the Board of Directors of the Company. General Director of Rosseti Centre provides the Board of Directors a report on the achievement of planned values of key performance indicators (hereinafter — KPI) at the end of each year.

Key performance indicators also form the basis of material incentives for General Director and senior management of the Company. General Director and senior managers are rewarded by the results of the implementation of KPIs, depending on the degree of KPIs execution for a reporting period (a year).

Key performance indicators for 20191

KPI name

Target value2

Implementation3

Quarterly KPI

Consolidated operating profit (EBITDA)

for 1 quarter, half-year and 9 months of the reporting year ≥ 0;
for the year ≥ 3,0%

1 quarter – not complete
2 quarter – complete
3 quarter – complete
4 quarter – complete

Consolidated net debt/EBITDA

1, 2, 3, 4 quarter ≤ 3,0

V

Implementation of the plan of measures to reduce receivables

≥ 100,0%

V

No increase in the number of major failures

No increase

V

Preventing the growth of the number of accident victims

No increase

V

Annual KPI

Consolidated net cash flow

≥ -2 802,8 mln RUB

V

Reduction of unit operating expenses (costs)

≥ 2,0%

V

Increase in capacity utilization of power grid equipment

complete

V

Level of electric energy losses

≤ 10,26 %

V

Reduction of unit investment expenditures

≤ 1,00

V

Workforce productivity

≥ 2,00%

V

Innovation activity efficiency

≥ 90%

V4

Implementation of a facility commissioning schedule

≥ 90%

V

Compliance with a grid connection deadline

≤ 1,1

V

Achieving the level of reliability of services provided

Concurrently:
1) KPI ≤ 1,00
2) Кi < 1,00

V

[1] Approved by the resolution of the Board of Directors of IDGC of Centre, PJSC dated 30.03.2017 (Minutes # 07/17 of 31.03.2017), in the edition approved by the resolution of the Board of Directors of IDGC of Centre, PJSC dated 03.08.2018 (Minutes # 24/18 of 03.08.2018), in the edition approved by the resolution of the Board of Directors of IDGC of Centre, PJSC dated 23.12.2019 (Minutes # 44/19 of 23.12.2019).

[2] The target KPI values for 2019 were approved by the Board of Directors of IDGC of Centre, PJSC dated 23.12.2019 (Minutes # 44/19 of 23.12.2019).

[3] Approved by the resolution of the Board of Directors of IDGC of Centre, PJSC dated 28.07.2020 (Minutes # 34/20 of 28.07.2020) – for quarters 1 and 4 of 2019 and the resolution of the Board of Directors of IDGC of Centre, PJSC dated 14.08.2020 (Minutes # 36/20 of 14.08.2020) for 2019.

[4] Approved by the resolution of the Board of Directors of IDGC of Centre, PJSC dated 29.12.2020 (Minutes # 64/20 of 29.12.2020).