Grid Connection
1 quarter
Grid connection in 2022 – 2026
Graph
Change*, %
* – change calculated with the rounded to the first decimal figures reflected in the table
|
Начальное изменение |
1Q 2022 |
1Q 2023 |
1Q 2024 |
1Q 2025 |
1Q 2026 |
|
Connected capacity, MW |
24,5 |
215,7 |
304,5 |
167,4 |
202,1 |
150,8 |
|
Number of concluded contracts, pcs. |
10,6 |
9 863 |
7 145 |
7 654 |
7 897 |
7 121 |
|
Number of connections, pcs. |
23,6 |
8 922 |
14 770 |
7 884 |
8 950 |
6 705 |
|
including connections up to 15 kW, pcs. |
25,3 |
8 350 |
13 978 |
7 309 |
8 404 |
6 208 |
Connected capacity broken down by Branches in 2022 – 2026
Graph
Change*, %
* – change calculated with the rounded to the first decimal figures reflected in the table
| MW |
Начальное изменение |
1Q 2022 |
1Q 2023 |
1Q 2024 |
1Q 2025 |
1Q 2026 |
|
Belgorodenergo |
-1,8 |
27,6 |
31,0 |
14,5 |
24,0 |
15,8 |
|
Bryanskenergo |
-57,8 |
4,3 |
6,2 |
6,8 |
4,2 |
4,5 |
|
Voronezhenergo |
111,6 |
52,7 |
51,3 |
41,2 |
44,4 |
37,2 |
|
Kostromaenergo |
89,6 |
18,2 |
17,9 |
15,5 |
12,2 |
8,2 |
|
Kurskenergo |
264,7 |
12,4 |
20,8 |
15,3 |
9,5 |
7,4 |
|
Lipetskenergo |
36,8 |
15,6 |
82,0 |
11,9 |
19,1 |
5,2 |
|
Orelenergo |
1,5 |
6,9 |
11,9 |
5,3 |
7,9 |
7,4 |
|
Smolenskenergo |
-27,0 |
18,7 |
19,1 |
12,8 |
30,8 |
16,8 |
|
Tambovenergo |
179,5 |
10,9 |
15,3 |
5,8 |
7,0 |
24,1 |
|
Tverenergo |
62,7 |
26,2 |
23,6 |
21,3 |
14,9 |
8,9 |
|
Yarenergo |
-33,1 |
22,2 |
25,4 |
17,0 |
28,1 |
15,3 |
Number of concluded contracts broken down by Branches in 2022 – 2026
Graph
Change*, %
* – change calculated with the rounded to the first decimal figures reflected in the table
| pcs. |
Начальное изменение |
1Q 2022 |
1Q 2023 |
1Q 2024 |
1Q 2025 |
1Q 2026 |
|
Belgorodenergo |
0,7 |
1 539 |
821 |
1 074 |
976 |
978 |
|
Bryanskenergo |
21,6 |
344 |
324 |
289 |
300 |
235 |
|
Voronezhenergo |
17,9 |
1 592 |
1 191 |
1 280 |
1 209 |
1 040 |
|
Kostromaenergo |
16,6 |
774 |
569 |
617 |
538 |
507 |
|
Kurskenergo |
4,4 |
589 |
407 |
467 |
511 |
817 |
|
Lipetskenergo |
46,6 |
1 004 |
875 |
852 |
958 |
745 |
|
Orelenergo |
38,8 |
433 |
241 |
263 |
381 |
230 |
|
Smolenskenergo |
25,8 |
971 |
539 |
612 |
590 |
530 |
|
Tambovenergo |
9,3 |
316 |
288 |
287 |
325 |
291 |
|
Tverenergo |
-16,2 |
1 219 |
858 |
926 |
928 |
753 |
|
Yarenergo |
6,7 |
1 082 |
1 032 |
987 |
1 181 |
995 |
Number of connections broken down by Branches in 2022 – 2026
Graph
Change*, %
* – change calculated with the rounded to the first decimal figures reflected in the table
| pcs. |
Начальное изменение |
1Q 2022 |
1Q 2023 |
1Q 2024 |
1Q 2025 |
1Q 2026 |
|
Belgorodenergo |
-8,4 |
1 275 |
1 748 |
1 010 |
1 065 |
857 |
|
Bryanskenergo |
-7,0 |
345 |
487 |
356 |
343 |
265 |
|
Voronezhenergo |
-12,9 |
1 279 |
2 858 |
1 416 |
1 765 |
1 362 |
|
Kostromaenergo |
50,0 |
786 |
1 056 |
603 |
838 |
508 |
|
Kurskenergo |
125,4 |
577 |
901 |
647 |
578 |
500 |
|
Lipetskenergo |
9,0 |
863 |
2 050 |
736 |
999 |
303 |
|
Orelenergo |
23,5 |
379 |
824 |
269 |
386 |
312 |
|
Smolenskenergo |
33,3 |
997 |
1 219 |
630 |
471 |
647 |
|
Tambovenergo |
220,9 |
353 |
642 |
322 |
387 |
340 |
|
Tverenergo |
79,7 |
1 028 |
1 500 |
908 |
927 |
496 |
|
Yarenergo |
53,4 |
1 040 |
1 485 |
987 |
1 191 |
1 115 |
Number of connections up to 15 kW broken down by Branches in 2022 – 2026
Graph
Change*, %
* – change calculated with the rounded to the first decimal figures reflected in the table
| pcs. |
Начальное изменение |
1Q 2022 |
1Q 2023 |
1Q 2024 |
1Q 2025 |
1Q 2026 |
|
Belgorodenergo |
-6,5 |
1 161 |
1 604 |
937 |
976 |
793 |
|
Bryanskenergo |
-2,3 |
337 |
470 |
338 |
323 |
251 |
|
Voronezhenergo |
-14,3 |
1 195 |
2 653 |
1 316 |
1 652 |
1 265 |
|
Kostromaenergo |
47,6 |
688 |
986 |
546 |
772 |
463 |
|
Kurskenergo |
118,0 |
545 |
859 |
620 |
565 |
490 |
|
Lipetskenergo |
7,1 |
812 |
1 962 |
671 |
933 |
271 |
|
Orelenergo |
23,9 |
368 |
810 |
253 |
373 |
286 |
|
Smolenskenergo |
38,4 |
927 |
1 161 |
569 |
401 |
572 |
|
Tambovenergo |
323,1 |
330 |
609 |
290 |
355 |
311 |
|
Tverenergo |
89,9 |
999 |
1 456 |
850 |
900 |
470 |
|
Yarenergo |
55,1 |
988 |
1 408 |
919 |
1 154 |
1 036 |
Connected capacity structure by categories of applicants in 2022 – 2026
Graph
Change*, %
* – the change is calculated on rounded to the first decimal place in the table
| % |
Начальное изменение |
1Q 2022 |
1Q 2023 |
1Q 2024 |
1Q 2025 |
1Q 2026 |
|
Up to 15 kW |
1,8 |
46,2 |
53,1 |
47,0 |
44,7 |
46,4 |
|
From 15 to 150 kW |
-4,6 |
20,5 |
18,6 |
27,3 |
21,0 |
15,6 |
|
From 150 to 670 kW |
-0,8 |
5,9 |
4,6 |
7,8 |
4,6 |
7,4 |
|
670 kW and above |
3,6 |
27,4 |
23,7 |
17,9 |
29,7 |
30,6 |
Connected capacity structure by categories of applicants in 1Q 2026