Productive potential indicators1 in 2018 – 2022
Graph
Change*, %
* – change calculated with the rounded to the first decimal figures reflected in the table
|
Начальное изменение |
9M 2018 |
9M 2019 |
9M 2020 |
9M 2021 |
9M 2022 |
Length of power lines (along ROW), km: |
-1,7 |
397 446 |
395 131 |
396 732 |
397 364 |
401 332 |
– Length of 35-110 kV Conductors (along ROW) |
-0,5 |
51 729 |
51 289 |
51 313 |
51 339 |
51 386 |
– Length of 0.4-10 kV Conductors (along ROW) |
-2,5 |
325 827 |
323 217 |
324 574 |
325 423 |
326 646 |
– Length of 0.4-110 kV Cables |
8,2 |
19 890 |
20 625 |
20 845 |
20 602 |
23 301 |
Capacity of Substations, MVA: |
0,0 |
54 375 |
54 226 |
54 732 |
55 063 |
56 031 |
– Capacity of 35-110 kV Substations |
0,2 |
34 380 |
34 400 |
34 721 |
34 854 |
34 998 |
– Capacity of 6-10/0.4 kV Transformer and Distribution Substations |
-0,4 |
19 995 |
19 826 |
20 011 |
20 209 |
21 033 |
Number of Substations, pcs: |
0,5 |
103 046 |
103 244 |
104 071 |
104 739 |
106 059 |
– Number of 35-110 kV Substations |
0,1 |
2 369 |
2 377 |
2 378 |
2 380 |
2 381 |
– Number of 6-10/0.4 kV Transformer and Distribution Substations |
0,5 |
100 677 |
100 867 |
101 693 |
102 359 |
103 678 |
Number of c.u. |
-0,5 |
2 307 445 |
2 421 449 |
2 533 651 |
2 650 963 |
2 778 486 |
Number of Distribution Zones, pcs |
0,0 |
277 |
274 |
253 |
217 |
218 |
1 – data presented with taking into account own and leased property, as well as property serviced under contracts
Length of 35-110 kV Conductors (along ROW)1 broken down by Branches in 2018 – 2022
Graph
Change*, %
* – change calculated with the rounded to the first decimal figures reflected in the table
Km |
Начальное изменение |
9M 2018 |
9M 2019 |
9M 2020 |
9M 2021 |
9M 2022 |
Belgorodenergo |
0,2 |
4 367 |
4 307 |
4 300 |
4 272 |
4 303 |
Bryanskenergo |
0,0 |
3 543 |
3 552 |
3 553 |
3 554 |
3 554 |
Voronezhenergo |
0,0 |
6 805 |
6 806 |
6 793 |
6 793 |
6 780 |
Kostromaenergo |
-2,5 |
4 204 |
4 184 |
4 184 |
4 184 |
4 189 |
Kurskenergo |
0,0 |
4 727 |
4 644 |
4 681 |
4 681 |
4 673 |
Lipetskenergo |
-1,2 |
3 838 |
3 811 |
3 826 |
3 809 |
3 822 |
Orelenergo |
-0,6 |
3 079 |
3 086 |
3 080 |
3 125 |
3 142 |
Smolenskenergo |
0,0 |
6 319 |
6 052 |
6 048 |
6 056 |
6 057 |
Tambovenergo |
-1,9 |
4 867 |
4 880 |
4 879 |
4 886 |
4 886 |
Tverenergo |
0,1 |
6 835 |
6 840 |
6 841 |
6 844 |
6 844 |
Yarenergo |
0,0 |
3 146 |
3 127 |
3 127 |
3 135 |
3 137 |
1 – data presented with taking into account own and leased property, as well as property serviced under contracts
Length of 0.4-10 kV Conductors (along ROW)1 broken down by Branches in 2018 – 2022
Graph
Change*, %
* – change calculated with the rounded to the first decimal figures reflected in the table
Km |
Начальное изменение |
9M 2018 |
9M 2019 |
9M 2020 |
9M 2021 |
9M 2022 |
Belgorodenergo |
-7,9 |
36 588 |
37 334 |
37 611 |
37 721 |
37 827 |
Bryanskenergo |
-0,2 |
21 790 |
22 264 |
22 352 |
22 566 |
22 605 |
Voronezhenergo |
0,3 |
45 484 |
43 905 |
44 226 |
44 338 |
44 529 |
Kostromaenergo |
-5,8 |
17 893 |
18 119 |
18 224 |
18 258 |
18 314 |
Kurskenergo |
0,5 |
32 385 |
29 340 |
29 458 |
29 473 |
29 483 |
Lipetskenergo |
-10,3 |
24 677 |
24 910 |
25 012 |
25 094 |
26 275 |
Orelenergo |
-9,2 |
22 941 |
23 262 |
23 247 |
23 183 |
23 219 |
Smolenskenergo |
0,2 |
32 879 |
33 073 |
33 181 |
33 456 |
33 602 |
Tambovenergo |
1,2 |
22 548 |
22 676 |
22 743 |
22 769 |
22 367 |
Tverenergo |
0,7 |
41 865 |
42 049 |
42 088 |
42 062 |
41 832 |
Yarenergo |
1,0 |
26 777 |
26 285 |
26 432 |
26 503 |
26 594 |
1 – data presented with taking into account own and leased property, as well as property serviced under contracts
Length of 0.4-110 kV1 Cables broken down by Branches in 2018 – 2022
Graph
Change*, %
* – change calculated with the rounded to the first decimal figures reflected in the table
Km |
Начальное изменение |
9M 2018 |
9M 2019 |
9M 2020 |
9M 2021 |
9M 2022 |
Belgorodenergo |
13,2 |
9 551 |
10 076 |
10 014 |
9 617 |
9 680 |
Bryanskenergo |
-0,1 |
144 |
146 |
171 |
180 |
194 |
Voronezhenergo |
5,5 |
367 |
401 |
405 |
426 |
462 |
Kostromaenergo |
6,0 |
1 637 |
1 666 |
1 700 |
1 713 |
1 757 |
Kurskenergo |
-0,4 |
336 |
298 |
306 |
308 |
322 |
Lipetskenergo |
12,8 |
1 180 |
1 235 |
1 254 |
1 298 |
3 725 |
Orelenergo |
-38,6 |
105 |
140 |
185 |
178 |
176 |
Smolenskenergo |
0,3 |
2 156 |
2 209 |
2 250 |
2 316 |
2 338 |
Tambovenergo |
9,0 |
316 |
323 |
332 |
290 |
286 |
Tverenergo |
5,8 |
908 |
931 |
973 |
990 |
1 016 |
Yarenergo |
4,5 |
3 171 |
3 201 |
3 255 |
3 286 |
3 345 |
1 – data presented with taking into account own and leased property, as well as property serviced under contracts
Capacity of 35-110 kV1 Substations broken down by Branches in 2018 – 2022
Graph
Change*, %
* – change calculated with the rounded to the first decimal figures reflected in the table
MVA |
Начальное изменение |
9M 2018 |
9M 2019 |
9M 2020 |
9M 2021 |
9M 2022 |
Belgorodenergo |
1,1 |
3 594 |
3 595 |
3 617 |
3 631 |
3 712 |
Bryanskenergo |
-0,6 |
2 477 |
2 440 |
2 489 |
2 607 |
2 606 |
Voronezhenergo |
-0,6 |
4 998 |
4 994 |
5 078 |
5 075 |
5 137 |
Kostromaenergo |
0,0 |
1 782 |
1 780 |
1 780 |
1 774 |
1 773 |
Kurskenergo |
0,0 |
3 479 |
3 477 |
3 601 |
3 594 |
3 594 |
Lipetskenergo |
0,5 |
3 038 |
3 038 |
3 006 |
3 006 |
3 136 |
Orelenergo |
3,0 |
1 881 |
1 911 |
1 910 |
1 926 |
1 895 |
Smolenskenergo |
0,0 |
3 062 |
3 114 |
3 170 |
3 170 |
3 170 |
Tambovenergo |
-0,1 |
2 571 |
2 591 |
2 597 |
2 597 |
2 597 |
Tverenergo |
-0,2 |
4 263 |
4 212 |
4 211 |
4 211 |
4 164 |
Yarenergo |
0,0 |
3 236 |
3 248 |
3 263 |
3 263 |
3 214 |
1 – data presented with taking into account own and leased property, as well as property serviced under contracts
Number of 35-110 kV1 Substations broken down by Branches in 2018 – 2022
Graph
Change*, %
* – change calculated with the rounded to the first decimal figures reflected in the table
Pcs |
Начальное изменение |
9M 2018 |
9M 2019 |
9M 2020 |
9M 2021 |
9M 2022 |
Belgorodenergo |
0,6 |
181 |
181 |
182 |
182 |
184 |
Bryanskenergo |
0,0 |
145 |
143 |
143 |
145 |
145 |
Voronezhenergo |
0,0 |
298 |
296 |
297 |
297 |
299 |
Kostromaenergo |
0,0 |
165 |
165 |
165 |
165 |
165 |
Kurskenergo |
0,0 |
285 |
285 |
286 |
286 |
286 |
Lipetskenergo |
0,0 |
201 |
201 |
200 |
200 |
206 |
Orelenergo |
0,7 |
144 |
147 |
145 |
146 |
145 |
Smolenskenergo |
0,0 |
252 |
253 |
254 |
254 |
254 |
Tambovenergo |
0,0 |
209 |
221 |
221 |
221 |
221 |
Tverenergo |
0,3 |
314 |
313 |
313 |
312 |
311 |
Yarenergo |
0,0 |
175 |
172 |
172 |
172 |
165 |
1 – data presented with taking into account own and leased property, as well as property serviced under contracts
Capacity of 6-10/0.4 kV1 Transformer and Distribution Substations broken down by Branches in 2018 – 2022
Graph
Change*, %
* – change calculated with the rounded to the first decimal figures reflected in the table
MVA |
Начальное изменение |
9M 2018 |
9M 2019 |
9M 2020 |
9M 2021 |
9M 2022 |
Belgorodenergo |
2,2 |
4 201 |
4 259 |
4 303 |
4 339 |
4 379 |
Bryanskenergo |
-0,5 |
780 |
776 |
811 |
828 |
833 |
Voronezhenergo |
1,3 |
1 872 |
1 849 |
1 870 |
1 896 |
1 932 |
Kostromaenergo |
1,0 |
1 545 |
1 545 |
1 544 |
1 537 |
1 533 |
Kurskenergo |
1,3 |
1 816 |
1 654 |
1 655 |
1 656 |
1 645 |
Lipetskenergo |
-0,5 |
1 686 |
1 709 |
1 712 |
1 728 |
2 462 |
Orelenergo |
-21,7 |
697 |
922 |
925 |
923 |
920 |
Smolenskenergo |
0,0 |
1 903 |
1 940 |
1 947 |
2 000 |
2 014 |
Tambovenergo |
-1,9 |
1 160 |
1 170 |
1 176 |
1 180 |
1 167 |
Tverenergo |
-1,4 |
1 941 |
1 951 |
1 971 |
1 987 |
1 985 |
Yarenergo |
1,4 |
2 394 |
2 051 |
2 097 |
2 136 |
2 162 |
1 – data presented with taking into account own and leased property, as well as property serviced under contracts
Number of 6-10/0.4 kV1 Transformer and Distribution Substations broken down by Branches in 2018 – 2022
Graph
Change*, %
* – change calculated with the rounded to the first decimal figures reflected in the table
Pcs. |
Начальное изменение |
9M 2018 |
9M 2019 |
9M 2020 |
9M 2021 |
9M 2022 |
Belgorodenergo |
1,0 |
13 423 |
13 571 |
13 711 |
13 830 |
13 934 |
Bryanskenergo |
-0,7 |
5 884 |
5 958 |
5 949 |
6 005 |
6 063 |
Voronezhenergo |
1,2 |
12 225 |
12 096 |
12 339 |
12 447 |
12 596 |
Kostromaenergo |
0,7 |
6 464 |
6 497 |
6 517 |
6 497 |
6 479 |
Kurskenergo |
0,8 |
10 198 |
9 408 |
9 507 |
9 549 |
9 537 |
Lipetskenergo |
-0,4 |
9 317 |
9 379 |
9 405 |
9 473 |
10 470 |
Orelenergo |
-4,7 |
5 825 |
5 902 |
5 868 |
5 817 |
5 754 |
Smolenskenergo |
0,3 |
9 593 |
9 790 |
9 805 |
9 977 |
10 055 |
Tambovenergo |
0,5 |
6 266 |
6 363 |
6 437 |
6 487 |
6 507 |
Tverenergo |
1,6 |
12 492 |
12 563 |
12 645 |
12 707 |
12 708 |
Yarenergo |
2,3 |
8 990 |
9 340 |
9 510 |
9 570 |
9 575 |
1 – data presented with taking into account own and leased property, as well as property serviced under contracts
Number of c.u.1 broken down by Branches in 2018 – 2022
Graph
Change*, %
* – change calculated with the rounded to the first decimal figures reflected in the table
c.u. |
Начальное изменение |
9M 2018 |
9M 2019 |
9M 2020 |
9M 2021 |
9M 2022 |
Belgorodenergo |
-4,4 |
344 822 |
362 137 |
378 028 |
390 762 |
400 108 |
Bryanskenergo |
0,2 |
132 468 |
163 521 |
176 713 |
185 863 |
189 127 |
Voronezhenergo |
5,3 |
269 908 |
279 977 |
306 017 |
319 251 |
324 326 |
Kostromaenergo |
9,2 |
151 994 |
161 509 |
168 207 |
177 934 |
180 233 |
Kurskenergo |
-15,5 |
190 972 |
206 724 |
208 909 |
219 845 |
226 288 |
Lipetskenergo |
-2,2 |
179 959 |
184 258 |
187 630 |
194 744 |
225 843 |
Orelenergo |
-4,3 |
127 720 |
141 280 |
151 186 |
158 064 |
157 718 |
Smolenskenergo |
-3,6 |
286 979 |
294 541 |
304 242 |
312 017 |
328 146 |
Tambovenergo |
0,4 |
142 034 |
145 754 |
148 074 |
149 134 |
174 745 |
Tverenergo |
6,8 |
241 192 |
241 441 |
255 835 |
282 572 |
302 457 |
Yarenergo |
7,1 |
239 398 |
240 306 |
248 811 |
260 776 |
269 495 |
1 – data presented with taking into account own and leased property, as well as property serviced under contracts
Level of physical deterioration of equipment1 in 2021 – 2022
Graph
Change*, %
* – the change is calculated on rounded to the first decimal place in the table
Name of equipment |
Начальное изменение |
30.06.2021 |
30.09.2021 |
31.12.2021 |
31.03.2022 |
30.06.2022 |
30.09.2022 |
Conductors 0.4-20 kV |
none |
72,4 |
72,6 |
72,7 |
73,0 |
73,2 |
73,4 |
Conductors 35-110 kV |
none |
83,8 |
84,0 |
84,1 |
84,3 |
84,5 |
84,7 |
Conductors 0.4-110 kV |
none |
75,3 |
75,5 |
75,6 |
75,9 |
76,1 |
76,3 |
Cables 0.4-20 kV |
none |
67,1 |
67,2 |
67,6 |
67,7 |
68,1 |
68,5 |
Cables 35-110 kV |
none |
41,2 |
42,2 |
39,7 |
40,7 |
41,4 |
40,6 |
Cables 0.4-110 kV |
none |
63,1 |
63,5 |
62,7 |
63,1 |
63,5 |
63,5 |
Power lines 35-110 kV |
none |
78,8 |
79,0 |
77,9 |
78,2 |
78,4 |
78,5 |
Power lines 3-20 kV |
none |
72,9 |
73,0 |
73,2 |
73,4 |
73,5 |
73,8 |
Power lines 0.4 kV |
none |
70,1 |
70,3 |
70,4 |
70,6 |
70,9 |
71,3 |
Transformer equipment 35-110 kV |
none |
85,8 |
86,0 |
86,2 |
86,4 |
86,6 |
86,7 |
Transformer equipment 3-110 kV |
none |
82,0 |
82,2 |
82,3 |
82,5 |
82,7 |
83,0 |
Switching devices 35-110 kV |
none |
75,1 |
75,5 |
75,8 |
76,1 |
76,3 |
76,7 |
Switching devices 3-110 kV |
none |
73,0 |
73,2 |
73,5 |
73,8 |
74,0 |
74,4 |
Substation equipment 35-110 kV |
none |
79,8 |
80,0 |
80,2 |
80,4 |
80,7 |
81,0 |
Substation equipment 3-110 kV |
none |
78,3 |
78,5 |
78,6 |
78,8 |
79,0 |
79,4 |
Total wear of Rosseti Centre |
none |
75,0 |
75,1 |
75,1 |
75,3 |
75,5 |
75,8 |