Productive potential

Productive potential

Productive potential indicators1 in 2020 – 2024

Graph
Начальное изменение 9M 2020 9M 2021 9M 2022 9M 2023 9M 2024
Length of power lines (along ROW), km: 0,4 396 732 397 364 401 332 403 970 406 438
– Length of 35-110 kV Conductors (along ROW) 0,0 51 313 51 339 51 386 51 381 51 453
– Length of 0.4-10 kV Conductors (along ROW) 0,4 324 574 325 423 326 646 328 395 330 358
– Length of 0.4-110 kV Cables 1,1 20 845 20 602 23 301 24 194 24 627
Capacity of Substations, MVA: 0,9 54 732 55 063 56 031 56 553 57 122
– Capacity of 35-110 kV Substations 0,9 34 721 34 854 34 998 35 125 35 362
– Capacity of 6-10/0.4 kV Transformer and Distribution Substations 0,9 20 011 20 209 21 033 21 428 21 760
Number of Substations, pcs: 0,8 104 071 104 739 106 059 107 429 108 519
– Number of 35-110 kV Substations 0,0 2 378 2 380 2 381 2 390 2 397
– Number of 6-10/0.4 kV Transformer and Distribution Substations 0,8 101 693 102 359 103 678 105 039 106 122
Number of c.u. 4,6 2 533 651 2 650 963 2 778 486 2 852 823 2 917 495
Number of Distribution Zones, pcs -7,7 253 217 218 218 219
1 – data presented with taking into account own and leased property, as well as property serviced under contracts

Length of 35-110 kV Conductors (along ROW)1 broken down by Branches in 2020 – 2024

Graph
Km Начальное изменение 9M 2020 9M 2021 9M 2022 9M 2023 9M 2024
Belgorodenergo -0,1 4 300 4 272 4 303 4 304 4 316
Bryanskenergo 0,0 3 553 3 554 3 554 3 554 3 554
Voronezhenergo -0,2 6 793 6 793 6 780 6 778 6 778
Kostromaenergo 0,0 4 184 4 184 4 189 4 189 4 195
Kurskenergo 0,8 4 681 4 681 4 673 4 666 4 706
Lipetskenergo 0,4 3 826 3 809 3 822 3 821 3 820
Orelenergo -0,2 3 080 3 125 3 142 3 142 3 142
Smolenskenergo -0,1 6 048 6 056 6 057 6 059 6 073
Tambovenergo 0,0 4 879 4 886 4 886 4 887 4 887
Tverenergo 0,0 6 841 6 844 6 844 6 845 6 846
Yarenergo 0,0 3 127 3 135 3 137 3 137 3 137
1 – data presented with taking into account own and leased property, as well as property serviced under contracts

Length of 0.4-10 kV Conductors (along ROW)1 broken down by Branches in 2020 – 2024

Graph
Km Начальное изменение 9M 2020 9M 2021 9M 2022 9M 2023 9M 2024
Belgorodenergo 0,7 37 611 37 721 37 827 38 194 38 453
Bryanskenergo 0,4 22 352 22 566 22 605 22 861 22 928
Voronezhenergo 0,7 44 226 44 338 44 529 44 726 45 241
Kostromaenergo 0,6 18 224 18 258 18 314 18 371 18 428
Kurskenergo 0,4 29 458 29 473 29 483 29 695 29 882
Lipetskenergo 0,4 25 012 25 094 26 275 26 462 26 773
Orelenergo -0,1 23 247 23 183 23 219 23 265 23 296
Smolenskenergo 0,3 33 181 33 456 33 602 33 907 34 132
Tambovenergo 0,3 22 743 22 769 22 367 22 412 22 637
Tverenergo 0,1 42 088 42 062 41 832 41 976 42 000
Yarenergo 0,6 26 432 26 503 26 594 26 527 26 586
1 – data presented with taking into account own and leased property, as well as property serviced under contracts

Length of 0.4-110 kV1 Cables broken down by Branches in 2020 – 2024

Graph
Km Начальное изменение 9M 2020 9M 2021 9M 2022 9M 2023 9M 2024
Belgorodenergo -0,6 10 014 9 617 9 680 10 095 10 259
Bryanskenergo 17,2 171 180 194 331 331
Voronezhenergo 1,1 405 426 462 486 540
Kostromaenergo 2,0 1 700 1 713 1 757 1 763 1 781
Kurskenergo 2,8 306 308 322 339 344
Lipetskenergo 1,5 1 254 1 298 3 725 3 824 3 875
Orelenergo 32,3 185 178 176 179 182
Smolenskenergo 1,9 2 250 2 316 2 338 2 492 2 588
Tambovenergo 3,0 332 290 286 319 321
Tverenergo 4,6 973 990 1 016 1 018 1 045
Yarenergo 1,7 3 255 3 286 3 345 3 349 3 361
1 – data presented with taking into account own and leased property, as well as property serviced under contracts

Capacity of 35-110 kV1 Substations broken down by Branches in 2020 – 2024

Graph
MVA Начальное изменение 9M 2020 9M 2021 9M 2022 9M 2023 9M 2024
Belgorodenergo 0,6 3 617 3 631 3 712 3 546 3 444
Bryanskenergo 2,0 2 489 2 607 2 606 2 624 2 648
Voronezhenergo 1,7 5 078 5 075 5 137 5 150 5 170
Kostromaenergo 0,0 1 780 1 774 1 773 1 774 1 774
Kurskenergo 3,6 3 601 3 594 3 594 3 657 3 665
Lipetskenergo -1,1 3 006 3 006 3 136 3 138 3 109
Orelenergo -0,1 1 910 1 926 1 895 1 945 1 947
Smolenskenergo 1,8 3 170 3 170 3 170 3 270 3 550
Tambovenergo 0,2 2 597 2 597 2 597 2 597 2 629
Tverenergo 0,0 4 211 4 211 4 164 4 205 4 205
Yarenergo 0,5 3 263 3 263 3 214 3 219 3 221
1 – data presented with taking into account own and leased property, as well as property serviced under contracts

Number of 35-110 kV1 Substations broken down by Branches in 2020 – 2024

Graph
Pcs Начальное изменение 9M 2020 9M 2021 9M 2022 9M 2023 9M 2024
Belgorodenergo 0,6 182 182 184 185 186
Bryanskenergo 0,0 143 145 145 146 147
Voronezhenergo 0,3 297 297 299 300 301
Kostromaenergo 0,0 165 165 165 165 165
Kurskenergo 0,4 286 286 286 288 288
Lipetskenergo -0,5 200 200 206 206 205
Orelenergo -1,4 145 146 145 146 146
Smolenskenergo 0,4 254 254 254 256 260
Tambovenergo 0,0 221 221 221 221 222
Tverenergo -0,3 313 312 311 312 312
Yarenergo 0,0 172 172 165 165 165
1 – data presented with taking into account own and leased property, as well as property serviced under contracts

Capacity of 6-10/0.4 kV1 Transformer and Distribution Substations broken down by Branches in 2020 – 2024

Graph
MVA Начальное изменение 9M 2020 9M 2021 9M 2022 9M 2023 9M 2024
Belgorodenergo 1,0 4 303 4 339 4 379 4 436 4 467
Bryanskenergo 4,5 811 828 833 898 892
Voronezhenergo 1,1 1 870 1 896 1 932 1 982 2 032
Kostromaenergo 0,0 1 544 1 537 1 533 1 535 1 552
Kurskenergo 0,1 1 655 1 656 1 645 1 669 1 723
Lipetskenergo 0,2 1 712 1 728 2 462 2 515 2 593
Orelenergo 0,2 925 923 920 928 916
Smolenskenergo 0,4 1 947 2 000 2 014 2 088 2 152
Tambovenergo 0,5 1 176 1 180 1 167 1 186 1 204
Tverenergo 1,0 1 971 1 987 1 985 2 015 2 022
Yarenergo 2,2 2 097 2 136 2 162 2 176 2 208
1 – data presented with taking into account own and leased property, as well as property serviced under contracts

Number of 6-10/0.4 kV1 Transformer and Distribution Substations broken down by Branches in 2020 – 2024

Graph
Pcs. Начальное изменение 9M 2020 9M 2021 9M 2022 9M 2023 9M 2024
Belgorodenergo 1,0 13 711 13 830 13 934 14 119 14 251
Bryanskenergo -0,2 5 949 6 005 6 063 6 188 6 244
Voronezhenergo 2,0 12 339 12 447 12 596 12 832 13 065
Kostromaenergo 0,3 6 517 6 497 6 479 6 500 6 556
Kurskenergo 1,1 9 507 9 549 9 537 9 695 9 819
Lipetskenergo 0,3 9 405 9 473 10 470 10 621 10 757
Orelenergo -0,6 5 868 5 817 5 754 5 817 5 831
Smolenskenergo 0,2 9 805 9 977 10 055 10 205 10 340
Tambovenergo 1,2 6 437 6 487 6 507 6 632 6 716
Tverenergo 0,7 12 645 12 707 12 708 12 831 12 844
Yarenergo 1,8 9 510 9 570 9 575 9 599 9 699
1 – data presented with taking into account own and leased property, as well as property serviced under contracts

Number of c.u.1 broken down by Branches in 2020 – 2024

Graph
c.u. Начальное изменение 9M 2020 9M 2021 9M 2022 9M 2023 9M 2024
Belgorodenergo 4,4 378 028 390 762 400 108 408 710 415 939
Bryanskenergo 8,1 176 713 185 863 189 127 192 325 193 524
Voronezhenergo 9,3 306 017 319 251 324 326 327 874 344 961
Kostromaenergo 4,1 168 207 177 934 180 233 183 758 188 372
Kurskenergo 1,1 208 909 219 845 226 288 231 334 233 065
Lipetskenergo 1,8 187 630 194 744 225 843 228 855 232 672
Orelenergo 7,0 151 186 158 064 157 718 160 057 160 918
Smolenskenergo 3,3 304 242 312 017 328 146 334 216 340 061
Tambovenergo 1,6 148 074 149 134 174 745 179 731 187 330
Tverenergo 6,0 255 835 282 572 302 457 310 260 322 935
Yarenergo 3,5 248 811 260 776 269 495 295 704 297 720
1 – data presented with taking into account own and leased property, as well as property serviced under contracts

Level of physical deterioration of equipment1 in 2023 – 2024

Graph
Name of equipment Начальное изменение 30.09.2023 31.12.2023 31.03.2024 30.06.2024 30.09.2024
Conductors 0.4-20 kV none 74,0 74,1 74,3 73,3 73,4
Conductors 35-110 kV none 85,3 85,4 85,6 85,7 85,9
Conductors 0.4-110 kV none 76,8 77,0 77,2 76,8 76,9
Cables 0.4-20 kV none 69,3 69,5 69,8 70,1 70,3
Cables 35-110 kV none 43,4 39,2 40,2 39,2 39,5
Cables 0.4-110 kV none 64,4 63,8 64,2 64,5 64,6
Power lines 35-110 kV none 78,9 78,5 78,8 78,8 78,7
Power lines 3-20 kV none 74,4 74,6 74,8 73,9 74,0
Power lines 0.4 kV none 72,1 72,3 72,5 69,9 70,1
Transformer equipment 35-110 kV none 87,4 87,6 87,8 88,0 88,2
Transformer equipment 3-110 kV none 83,6 83,7 84,0 84,1 84,3
Switching devices 35-110 kV none 77,8 78,1 78,3 78,6 78,9
Switching devices 3-110 kV none 75,6 75,8 76,1 76,4 76,6
Substation equipment 35-110 kV none 82,0 82,2 82,4 82,7 82,9
Substation equipment 3-110 kV none 80,3 80,5 80,8 81,0 81,2
Total wear of Rosseti Centre none 76,6 76,6 76,9 76,7 76,8
1 – data presented with taking into account own and leased property, as well as property serviced under contracts