Investment activity
2 quarter
Quarterly amount of investments in 2020 – 2024
Graph
Change*, %
* – change is calculated on the basis of the indicators presented in the table and rounded to the nearest tenth
|
Начальное изменение |
2Q '20 |
2Q '21 |
2Q '22 |
2Q '23 |
2Q '24 |
CAPEX without VAT, million RUR |
17,2 |
2 883,8 |
2 300,9 |
2 123,2 |
3 380,9 |
3 457,9 |
- Grid connection |
34,4 |
1 460,7 |
918,3 |
1 139,7 |
2 329,4 |
2 413,3 |
- New construction, million RUR |
-90,6 |
6,0 |
121,6 |
19,0 |
16,6 |
35,8 |
- Retrofitting and reconstruction, million RUR |
11,2 |
1 268,6 |
1 142,8 |
629,7 |
705,9 |
642,5 |
- Other, million RUR |
-11,7 |
148,5 |
118,2 |
334,8 |
329,0 |
366,3 |
Fixed assets commissioned without VAT, million RUR |
-22,5 |
1 808,4 |
2 734,7 |
2 219,5 |
2 564,7 |
3 407,2 |
Financing with VAT, million RUR |
-13,7 |
2 362,8 |
3 181,4 |
2 575,4 |
4 554,7 |
5 172,3 |
Сapacity commissioned, km |
-45,1 |
549,9 |
530,4 |
310,9 |
574,1 |
668,8 |
Сapacity commissioned, MVA |
-47,1 |
47,0 |
46,2 |
68,7 |
54,8 |
89,1 |