Investment activity
9 months
Quarterly amount of investments in 2020 – 2024
Graph
Change*, %
* – change is calculated on the basis of the indicators presented in the table and rounded to the nearest tenth
|
Начальное изменение |
9M '20 |
9M '21 |
9M '22 |
9M '23 |
9M '24 |
CAPEX without VAT, million RUR |
22,4 |
7 876,1 |
6 779,9 |
6 478,5 |
10 427,9 |
10 635,6 |
- Grid connection |
22,2 |
3 609,3 |
3 068,3 |
3 660,4 |
7 109,7 |
6 451,9 |
- New construction, million RUR |
-45,8 |
119,7 |
284,1 |
108,3 |
117,9 |
201,3 |
- Retrofitting and reconstruction, million RUR |
42,9 |
3 751,1 |
3 014,5 |
1 936,5 |
2 317,5 |
2 770,7 |
- Other, million RUR |
-38,0 |
396,0 |
412,9 |
773,3 |
882,9 |
1 211,7 |
Fixed assets commissioned without VAT, million RUR |
23,2 |
6 733,3 |
7 492,8 |
5 923,8 |
8 868,7 |
9 594,8 |
Financing with VAT, million RUR |
9,1 |
8 258,4 |
11 123,2 |
10 135,2 |
13 394,9 |
15 408,8 |
Сapacity commissioned, km |
-35,5 |
1 460,5 |
1 500,7 |
1 038,4 |
2 011,4 |
1 934,6 |
Сapacity commissioned, MVA |
17,2 |
268,6 |
142,6 |
193,6 |
200,2 |
425,8 |