Investment activity

Annual indicators

Annual amount of investments in 2018 – 2022

Graph
Начальное изменение 2018 2019 2020 2021 2022
CAPEX without VAT, billion RUR, including: 3,4 12,2 11,8 13,8 14,1 12,1
- Grid connection -2,0 4,9 4,5 5,0 5,2 5,7
- New construction, billion RUR -57,1 0,3 0,5 0,3 1,0 0,9
- Retrofitting and reconstruction, billion RUR 19,0 6,9 6,8 8,3 7,8 4,0
- Others, billion RUR -50,0 0,1 0,1 0,1 0,1 1,4
Fixed assets commissioned without VAT, billion RUR 7,6 12,7 11,2 12,2 15,4 12,4
Financing with VAT, billion RUR 2,1 14,5 13,6 14,0 16,9 15,1
Сapacity commissioned, km -11,7 3598,0 3350,9 2098,3 2700,8 2459,2
Сapacity commissioned, MVA -32,9 376,0 425,6 374,3 386,0 362,8

Main indicators of the Investment program 2023 – 20271


2023 2024 2025 2026 2027
CAPEX without VAT, million RUR 18 120,8 16 328,6 15 534,0 14 677,8 13 858,8
Fixed assets commissioned without VAT, million RUR 17 905,3 17 113,0 16 172,1 14 465,0 13 905,3
Financing with VAT, million RUR 20 419,9 18 590,7 19 772,9 17 232,6 17 363,4
Сapacity commissioned, km 3 263 3 237 2 477 2 408 2 831
Сapacity commissioned, MVA 314 397 473 575 198
1 – according to Order of the Ministry of Energy from 19.12.2023 №27@

The Investment program structure (CAPEX) (without VAT) for 2023 – 2027 broken down by the branches1


million RUR 2023 2024 2025 2026 2027
Belgorodenergo 3 419,9 3 626,7 4 797,2 2 903,2 2 653,0
Bryanskenergo 962,1 805,9 819,8 803,2 891,3
Voronezhenergo 3 138,1 3 295,1 2 387,4 2 993,3 2 405,8
Kostromaenergo 1 036,6 1 173,8 1 144,7 1 189,1 999,8
Kurskenergo 1 502,9 824,2 752,5 798,6 883,0
Lipetskenergo 2 421,3 1 913,2 1 417,7 1 485,2 1 700,8
Orelenergo 555,9 583,2 572,2 563,5 550,0
Smolenskenergo 1 299,6 999,6 887,9 969,2 1 150,9
Tambovenergo 868,7 816,3 713,8 802,7 618,5
Tverenergo 674,4 415,6 445,1 327,1 384,7
Yarenergo 2 195,8 1 875,1 1 595,6 1 842,7 1 621,0
Executive office 45,3 0,0 0,0 0,0 0,0
Total 18 120,8 16 328,6 15 534,0 14 677,8 13 858,8
1 – according to Order of the Ministry of Energy from 19.12.2023 №27@

Priority investment projects1


Project name,
location of the facility

Goals and objectives of the project

Design capacity
(MVA, km)

Work within the project

Implementation period, financing % at the reporting date

Funding, thous. RUB

planned

performed

Reconstruction of 110/10 kV South Substation with replacement of power transformers of 2х40 MVA for 2х32 and 2х6.3 MVA, installation of a rapidly erected building: indoor Switchgear-6kV, indoor Switchgear-10kV, a substation control building with relay protection and automation panels, remote control and digital communications channel (transformer capacity 76.6 MVA), Belgorod region

The project provides for the renovation of basic production assets, the elimination of the power deficit of the Power Centre, and the improvement of the reliability of electricity supply to customers, creating opportunities to connect new customersers

76,6 МВА

Reconstruction of SS-110 kV with installation of two additional transformers 2х6.3 MVA and replacement of existing 2х40MVA for 2х32 MVA

2012-2025
19%

635 421

121 779

Reconstruction of 110/35/10 kV Korocha Substation with the transfer of SS to a new site. Instead of three transformers TDTN-16000/110/35/10 two transformers TDTN-25000/110/35/10 are installed, equipment of outdoor Switchgear 110 kV under the circuit №110-13, outdoor Switchgear 35 kV under the circuit №35-9, indoor Switchgear-10 kV in a rapidly erected building (power increase by 2 MVA), Belgorod region

The project provides for the renovation of basic production assets, the elimination of the power deficit of the Power Centre, and the improvement of the reliability of electricity supply to customers

64 МВА

Reconstruction of a two transformer Substation 110/35/10 kV with installation of transformers 2х25 MVA

2016-2025
11%

1 186 378

135 927

Reconstruction of the 110 kV overhead line N. Oskol - V. Pokrovka with replacement of wire, poles, ground wire with a change in the boundaries of the right-of-way and security zones (the length of 43.2 km)

The project provides for renovation of fixed production assets to ensure high-quality and uninterrupted transmission of electricity

43,2 km

Reconstruction of the 110 kV overhead line with replacement of wire, poles, ground wire

2025-2028
0%

575 434

0

Reconstruction of the 2-circuit overhead line 110 kV Stary Oskol-500 - Central with replacement of wire, poles, ground wire, with a change in the boundaries of the right-of-way and the security zone (the length of 10.7 km)

The project provides for renovation of fixed production assets to ensure high-quality and uninterrupted transmission of electricity

10,7 km

Reconstruction of the 110 kV overhead line with replacement of wire, poles, ground wire

2024-2027
0%

352 843

0

Reconstruction of the 2-circuit 110 kV GTU CHP Luch - Cheremoshnoye with replacement of wire, poles, ground wire, with a change in the boundaries of the right-of-way and the security zone (the length of 35.9 km)

The project provides for renovation of fixed production assets to ensure high-quality and uninterrupted transmission of electricity

35,9 km

Reconstruction of the 110 kV overhead line with replacement of wire, poles, ground wire

2024-2027
0%

302 962

0

Technical re-equipment of the 35/6 kV Lebedi substation with replacement of power transformers (5.6 and 4 MVA with 2x4 MVA), 35 kV circuit breakers (2 pcs), 35 kV disconnectors (8 pcs), 6 kV bays (21 pcs) (transformer power 8.0 MVA)

Ensuring reliable power supply to consumers and trouble-free operation of the distribution grid complex

8 MVA

Technical re-equipment of the 35/6 kV substation with replacement of power transformers for 2x4 MVA, 35 kV circuit breakers (2 pcs), 35 kV disconnectors (8 pcs), 6 kV bays (21 pcs)

2026-2028
0%

304 184

0

Construction of the 110/35/10 kV Zadonskaya substation with 2x16 MVA transformers (transformer capacity 32 MVA)

The project provides for construction of a new power centre to eliminate the shortage of power and improve the reliability of power supply to consumers

32 MVA

Construction of the 110/35/10 kV 2-transformer substation with installation of 2x16 MVA transformers

2018-2024
1%

718 192

4 043

1 – in accordance with the Investment Program, approved by the Ministry of Energy on 06.12.2022 №35@