Site colours:
Zoom:

Investment activity

Annual indicators

Annual amount of investments in 2019 – 2023

Graph
Начальное изменение 2019 2020 2021 2022 2023
CAPEX without VAT, million RUR, including: -3,2 11 836,1 13 772,9 14 146,7 12 064,2 18 657,9
- Grid connection -10,0 4 452,5 5 024,0 5 163,8 5 742,3 10 286,0
- New construction, million RUR 11,4 292,0 334,5 959,5 871,7 428,8
- Retrofitting and reconstruction, million RUR 22,0 5 820,4 7 117,1 6 561,3 4 023,5 5 602,0
- Others, million RUR -43,5 1 271,2 1 297,3 1 462,0 1 426,7 2 341,1
Fixed assets commissioned without VAT, million RUR -11,5 11 245,5 12 240,9 15 384,1 12 444,7 18 443,3
Financing with VAT, million RUR -6,4 13 562,7 14 038,9 16 859,4 15 144,4 20 665,6
Сapacity commissioned, km -6,9 3 350,9 2 098,3 2 700,8 2 459,2 3 365,6
Сapacity commissioned, MVA 13,2 425,6 374,3 386,0 362,8 451,1

Main indicators of the Investment program 2023 – 20271


2023 2024 2025 2026 2027
CAPEX without VAT, million RUR 18 120,8 16 328,6 15 534,0 14 677,8 13 858,8
Fixed assets commissioned without VAT, million RUR 17 905,3 17 113,0 16 172,1 14 465,0 13 905,3
Financing with VAT, million RUR 20 419,9 18 590,7 19 772,9 17 232,6 17 363,4
Сapacity commissioned, km 3 263 3 237 2 477 2 408 2 831
Сapacity commissioned, MVA 314 397 473 575 198
1 – according to Order of the Ministry of Energy from 19.12.2023 №27@

The Investment program structure (CAPEX) (without VAT) for 2023 – 2027 broken down by the branches1


million RUR 2023 2024 2025 2026 2027
Belgorodenergo 3 419,9 3 626,7 4 797,2 2 903,2 2 653,0
Bryanskenergo 962,1 805,9 819,8 803,2 891,3
Voronezhenergo 3 138,1 3 295,1 2 387,4 2 993,3 2 405,8
Kostromaenergo 1 036,6 1 173,8 1 144,7 1 189,1 999,8
Kurskenergo 1 502,9 824,2 752,5 798,6 883,0
Lipetskenergo 2 421,3 1 913,2 1 417,7 1 485,2 1 700,8
Orelenergo 555,9 583,2 572,2 563,5 550,0
Smolenskenergo 1 299,6 999,6 887,9 969,2 1 150,9
Tambovenergo 868,7 816,3 713,8 802,7 618,5
Tverenergo 674,4 415,6 445,1 327,1 384,7
Yarenergo 2 195,8 1 875,1 1 595,6 1 842,7 1 621,0
Executive office 45,3 0,0 0,0 0,0 0,0
Total 18 120,8 16 328,6 15 534,0 14 677,8 13 858,8
1 – according to Order of the Ministry of Energy from 19.12.2023 №27@

Priority investment projects1


Project name,
location of the facility

Goals and objectives of the project

Design capacity
(MVA, km)

Work within the project

Implementation period, financing % at the reporting date

Funding, thous. RUB

planned

performed

Construction of 110/10 kV Zhemchuzhnaya Substation, for grid connection of JSC SZ Directorate of the Southwestern District, contract No. 42309778 dated 25 November 2022, Belgorod (over 670 kW; transformer capacity 80.0 MVA)

The project provides for the construction of a new power centre for grid connection and increased reliability of power supply to consumers

80 MVA

Construction of a two-transformer substation 110/10 kV with installation of 2x40 MVA transformers

2023-2025
0%

1 057 052,87

0,00

Construction of 110/35/10 kV Zadonskaya Substation with 2x16 MVA transformers (transformer capacity 32 MVA)

The project provides for the construction of a new power centre to eliminate the power shortage and increase the reliability of power supply to consumers

32 MVA

Construction of a two-transformer 110/35/10 kV substation with installation of 2x16 MVA transformers

2018-2026
4%

718 192,23

25 159,03

1 – according to Order of the Ministry of Energy of Russia dated 19 December 2023 No. 27@