* — the change is calculated on the basis of the indicators presented in the table and rounded to the nearest tenth
Billion kW*h
Начальное изменение
1H 2018
1H 2019
1H 2020
1H 2021
1H 2022
Supply to the grid
-15.1
27.5
26.8
25.9
27.3
27.4
Productive supply1
-16.3
24.6
24.0
23.3
24.6
24.6
Total losses
-3.33
2.9
2.8
2.7
2.7
2.8
Total losses, %
1.35
10.61
10.54
10.37
9.92
10.26
Electricity transmission services2
-16.5
23.8
23.3
22.6
23.9
24.1
1 — productive supply within the joint operation (taking into account losses of TGOs) 2 — Taking into account the volume of services for the transmission of electrical energy in the territory of the «pick-up» of the functions of the supplier of last resort (boiler productive supply)
Electrical energy supply to the grid broken down by Branches in 2018 – 2022
* - the change is calculated on rounded to the first decimal place in the table
bln kW/h
Начальное изменение
1H 2018
1H 2019
1H 2020
1H 2021
1H 2022
Belgorodenergo
-42.4
3.4
3.2
3.2
3.2
3.2
Bryanskenergo
0.0
1.8
1.8
1.6
1.7
1.7
Voronezhenergo
5.1
4.1
4.0
4.0
4.2
4.3
Kostromaenergo
0.0
1.2
1.2
1.1
1.3
1.2
Kurskenergo
-46.4
1.5
1.5
1.5
1.6
1.6
Lipetskenergo
-29.4
2.4
2.2
2.3
2.4
2.4
Orelenergo
0.0
1.1
1.0
1.0
1.1
1.1
Smolenskenergo
5.9
1.8
1.7
1.6
1.8
1.8
Tambovenergo
0.0
1.4
1.4
1.4
1.4
1.4
Tverenergo
0.0
2.3
2.2
2.2
2.4
2.4
Yarenergo
0.0
3.0
2.9
2.8
3.0
3.0
2 - Taking into account the volume of services for the transmission of electric energy in the territory of the "pick-up" of the functions of the supplier of last resort (boiler productive supply)
Structure of productive supply by voltage levels (volume of electricity transmission services)
1Taking into account the volume of services for electricity transmission in the territory of “pick-up” of the functions of the supplier of last resort (boiler productive supply)
Structure of productive supply by voltage levels in 1H 2022
* - change calculated with the rounded to the first decimal figures reflected in the table
Начальное изменение
1H 2018
1H 2019
1H 2020
1H 2021
1H 2022
Connected capacity, MW
-12.4
346.6
276.1
559.9
329.4
429.8
Number of concluded contracts, pcs.
-6.9
19 856
18 114
13 697
20 537
23 906
Number of connections, pcs.
-8.1
16 787
14 838
13 582
14 853
17 647
including connections up to 15 kW, pcs.
-10.0
15 713
13 886
12 432
13 746
16 495
Average term of performance of grid connection contracts with activities on the part of the grid company (“contract-notification”) under the Doing Business category, days
-28.4
83
89
63
60
71
Connected capacity broken down by Branches in 2018 – 2022